Resource work availability report

M

Mocha

Dear all,
I noticed in resource work availibility report (in visual report Ms
Project profesional 2007), there are some big question in my mind.
a. the actual work doesn't give the right value.
The cause of problem is when user fill timesheet in PWA and they fill
administrative time (type working). In ms Project profesional it is noted in
"other project and commitments" as work time(the actual work is blank). It
makes the actual work in resource work availibility report doesnt give the
right value.
b. The remaining availibilty in resource work availibility report and
resource usage view in project profesional doesn't match.
I have tried to compare day per day between value in resource usage (menu
View -> resource usage) and in the resource work availibility report
Could someone explain this situation?
Thannk you....
 
M

Mike Glen

Hi Mocha,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top