Hello,
The basics:
-A Fixed Work type task with 4 working days duration, starting on a
non-holiday Monday in a non-holiday week;
-A defined and assigned 7-day work week, 10-hour day calendar;
-1 resource entered at 127.08 hours (directly from an estimate) for the task.
For some reason the task ending on a Friday spreads the resource work as
follows:
M: 25.42h, T: 31.77h, W: 31.77h, TH: 31.77h, F: 6.35h
So even though the task is defined as 4 days duration, the spreading is
taking 6.35h from the first day and putting it into a "fifth" day.
Why?
The basics:
-A Fixed Work type task with 4 working days duration, starting on a
non-holiday Monday in a non-holiday week;
-A defined and assigned 7-day work week, 10-hour day calendar;
-1 resource entered at 127.08 hours (directly from an estimate) for the task.
For some reason the task ending on a Friday spreads the resource work as
follows:
M: 25.42h, T: 31.77h, W: 31.77h, TH: 31.77h, F: 6.35h
So even though the task is defined as 4 days duration, the spreading is
taking 6.35h from the first day and putting it into a "fifth" day.
Why?