S
Sequoia D. Schroeder
I have a task (Order Equipment) with a duration of 8 weeks
to allow for delivery time. I want to assign a resource
(Buyer) to the task for, say, 1 day at the beginning of
the task, and 1 day at the end of the task. In between
should be "wait time." I would rather have this task be
one task rather than two or three tasks linked together.
I tried adding a resource called "Wait Time" but when I
gave "Buyer" 1 day the Assign Resource dialog, Project
assigned 0.2 hrs each day of the task, and there seems to
be no way to "front load" (or front and back load) the
resources hours on the task.
Is there a way to accomplish this without creating a
separate task for wait time?
Thanks!
- Sequoia
note: e.mail above is closed due to excessive spam/viruses
resulting from posting it to this forum previously.
if you wish to e.mail me
sequoia UNDERSCORE s AT yahoo DOT com
humans can figure that out ... spambots should choke on it.
to allow for delivery time. I want to assign a resource
(Buyer) to the task for, say, 1 day at the beginning of
the task, and 1 day at the end of the task. In between
should be "wait time." I would rather have this task be
one task rather than two or three tasks linked together.
I tried adding a resource called "Wait Time" but when I
gave "Buyer" 1 day the Assign Resource dialog, Project
assigned 0.2 hrs each day of the task, and there seems to
be no way to "front load" (or front and back load) the
resources hours on the task.
Is there a way to accomplish this without creating a
separate task for wait time?
Thanks!
- Sequoia
note: e.mail above is closed due to excessive spam/viruses
resulting from posting it to this forum previously.
if you wish to e.mail me
sequoia UNDERSCORE s AT yahoo DOT com
humans can figure that out ... spambots should choke on it.