Resource work value is shown in seconds instead of days

R

Ran @Comverse

Hi,

In the resource sheet I see the resources' work value in seconds instead of
days and I can't find any option to change it.

Please assist,
Thanks,
Ran.
 
J

Jan De Messemaeker

Hi,

You'll never see seconds... Project does not know this unit, it calculates
everything in tenths of minutes.
This being said, Tools, Options, Schedule, Work is expressed in... select
the appropriate unit.
If you still see anything else, you are looking at a custom field, not the
work field.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

JulieS

Ran,
It appears as though replies that are not posted through this web page are
being lost. Jan did reply to your message earlier today and I've copied his
reply below.
----------------------------------------------------------
Jan De Messemaeker wrote:

Hi,

You'll never see seconds... Project does not know this unit, it calculates
everything in tenths of minutes.
This being said, Tools, Options, Schedule, Work is expressed in... select
the appropriate unit.
If you still see anything else, you are looking at a custom field, not the
work field.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 