Resource Working Hours

M

Marc

Is ther a way to have a resource work hours that "cross" midnight, i.e., a
resource that works from 8pm to 3am. I can adjust the working hours per day,
but only from 12am to 11:59pm. It doesn't look like I can "cross" midnight.
Thanks in advance.
 
J

JulieS

Hi Marc,

Take a look at the "Night Shift" base calendar is MS Project (Tools >
Change Working time) to see an example of a calendar setup that crosses
midnight.

I hope this helps. Let us know how you get along.

Julie
 
G

Gérard Ducouret

Hi Marc,

There is no way to have a resource work hours that "cross" midnight. You
have to manage 2 time slots:
From 00:00 To 03:00
From 20:00 To 00:00

Gérard Ducouret
 