Michael Waite
hi,
I am finding impossible in Ptoject 2000 to specify a one
off working time for a resource. e.g. 4 hrs on 26 April
2004. No cycle.
I have tried making the entire resource calander non-
working time first but that is prevented. I have tried
making each day at a time non-working without success.
I must be missing something simple?