Whenever
I add a resource to a task, project arbitrarily
changes the duration of the task and I can not correct
it. I think it does some kind of hours per man
calculation or something.. Does anyone know how to
disable it or how to enter resources without changing
any other value??
 
D

Dale Howard [MVP]

BJ --

If the task is Effort Driven, then Microsoft Project proportionally splits
the Remaining Work on the task between the existing resources and the
newly-assigned resource. To disable this behavior on any task, double-click
the task, select the Advanced tab, and deselect the Effort Driven option.
Hope this helps.
 
J

Jan De Messemaeker

Sorry John, if the task is Effort driven even a fixed duration task will see
its duration change when a resource is added or withdrawn
HTH
 