Pal Ahuja - India
Hi
I am using MS-Project 2002. I have following problems while planning projects.
When I allocate multiple resource to a task and each resource has certain % of time allocated to it, the number of hours calcualted for the task remain same.
e.g. I have a task starting 2nd Feb'04 to 15th Apr'04. Two resources, say A and B, have been allocated on this task. Resource A is to work for 50% of his time and resource B for 100%. The task is to be completed in 432 hours. If we calculate the time between 2nd Feb and 15th Apr, the total number of hours are 432. Since there are 2 resources A and B, actually this task should be over earlier or the final date should get changed automatically. I would like, number of hours to be the limiting factor and final date shoud be decided accordingly. Please advise me how to do this.
Thanks
Pal Ahuj
Indi
I am using MS-Project 2002. I have following problems while planning projects.
When I allocate multiple resource to a task and each resource has certain % of time allocated to it, the number of hours calcualted for the task remain same.
e.g. I have a task starting 2nd Feb'04 to 15th Apr'04. Two resources, say A and B, have been allocated on this task. Resource A is to work for 50% of his time and resource B for 100%. The task is to be completed in 432 hours. If we calculate the time between 2nd Feb and 15th Apr, the total number of hours are 432. Since there are 2 resources A and B, actually this task should be over earlier or the final date should get changed automatically. I would like, number of hours to be the limiting factor and final date shoud be decided accordingly. Please advise me how to do this.
Thanks