Marco
What is the best approach to work with tasks that are assigned to a
subcontracting company.
We want to include the task in our project plan and use the company name as
resource name when assigning the task.
Should I use local resources or is there a better way ? I read that it is
not recommended to user local resources that can cause spooler errors...
thanks
Marco