Resources are overallocated, but Resource Usage View doesn't highl

H

Hung

Hi all,
In my project plan, the resources were actually overallocated, the Resource
Sheet does highlight them as red, the Resource Graph does show red portion >
100%
But in Resource Usage view, all the names are not highlighted in red color,
even in the right pane, there are some weeks the hours allocated to a
resource are > 80h/week

If I group by Overallocated, then there are resources put in Overallocated Yes
but they are not highlighted the period the resources are overallocated.

What am I missing ?
Thanks
 
J

Jan De Messemaeker

Hi,

"Overallocated" for Project means loaded for more than the max units for at
least one minute in the schedule.
The resoruce graph actually shows that (Peak Units)
In the resource graph right click on the graphical part and select Work or
Percent allocation
Then read FAQ 34. Overallocation occurring in less than one day (URL of the
FAQs inmy signature)

HTH
 