Hi all,
In my project plan, the resources were actually overallocated, the Resource
Sheet does highlight them as red, the Resource Graph does show red portion >
100%
But in Resource Usage view, all the names are not highlighted in red color,
even in the right pane, there are some weeks the hours allocated to a
resource are > 80h/week
If I group by Overallocated, then there are resources put in Overallocated Yes
but they are not highlighted the period the resources are overallocated.
What am I missing ?
Thanks
In my project plan, the resources were actually overallocated, the Resource
Sheet does highlight them as red, the Resource Graph does show red portion >
100%
But in Resource Usage view, all the names are not highlighted in red color,
even in the right pane, there are some weeks the hours allocated to a
resource are > 80h/week
If I group by Overallocated, then there are resources put in Overallocated Yes
but they are not highlighted the period the resources are overallocated.
What am I missing ?
Thanks