R
rajanmisra
Hi
We had to fix a few projects which had resources assigned at the
summary level.
Steps followed in fixing:
1. Saved the project file as .mpp file.
2.Deleted the project from PWA.
3.Delete the resource from the summary level in the .mpp file.
4.Published the saved .mpp file to the server.
The issue is that the actuals of the project has moved correctly , but
still it is showing unsubmitted timesheets.
Thanks and regards
Rajan
We had to fix a few projects which had resources assigned at the
summary level.
Steps followed in fixing:
1. Saved the project file as .mpp file.
2.Deleted the project from PWA.
3.Delete the resource from the summary level in the .mpp file.
4.Published the saved .mpp file to the server.
The issue is that the actuals of the project has moved correctly , but
still it is showing unsubmitted timesheets.
Thanks and regards
Rajan