P
Pearl
Hello,
We have Project Server 2003.
I have a resource that works at 2 different projects (gantts).
For the first project he is available from March, 1st. and for the second
project he is available from May, 1st.
How should I update his availabiltiy per project ?
I have the same question when the resource should work on 2 projects at the
same time with 50% for each one.
Thanks
Pearl
We have Project Server 2003.
I have a resource that works at 2 different projects (gantts).
For the first project he is available from March, 1st. and for the second
project he is available from May, 1st.
How should I update his availabiltiy per project ?
I have the same question when the resource should work on 2 projects at the
same time with 50% for each one.
Thanks
Pearl