A
Andrea the Frustrated PM
I have to schedule resources that are only available to work on a project for
say 80% of their time. If I change the units to 80 for the resource and
assign them to a 2 week project, shouldn't it lengthen the time it takes to
complete the project basecd on the fact that he will not be working full
days? All my resources are less than 100% and i am struggling to make this
work. Any suggestions???
say 80% of their time. If I change the units to 80 for the resource and
assign them to a 2 week project, shouldn't it lengthen the time it takes to
complete the project basecd on the fact that he will not be working full
days? All my resources are less than 100% and i am struggling to make this
work. Any suggestions???