C
coleyparka
Hi
I'm trying to use ms project to calculate exactly how many resources
need to complete a given task by a set deadline. I currently do not hav
enough resources, but I know how much work there is to be done and whe
it needs to be done by, but I can't seem to find anyway of Projec
showing me exactly how many extra resources I actually need to hire i
order to meet the deadline. All it seems to offer is the option o
moving the deadline or decreasing the work. I can see that this is
kind of backwards calculation to the way that Project normally works
but cannot believe that it doesn't have the functionally to do it. Am
missing something very obvious?
Cheers
Coleypark
I'm trying to use ms project to calculate exactly how many resources
need to complete a given task by a set deadline. I currently do not hav
enough resources, but I know how much work there is to be done and whe
it needs to be done by, but I can't seem to find anyway of Projec
showing me exactly how many extra resources I actually need to hire i
order to meet the deadline. All it seems to offer is the option o
moving the deadline or decreasing the work. I can see that this is
kind of backwards calculation to the way that Project normally works
but cannot believe that it doesn't have the functionally to do it. Am
missing something very obvious?
Cheers
Coleypark