Resources customized fields in task view

J

julnar

Hi,
How to display customized resource field in task view ?
Exemple resource texte1 "skill" in task view
As principle, I allocate only one ressource per task
Thanks
 
M

Mike Glen

Hi julnar,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 37 - Custom Fields in Tables. FAQs,
companion products and other useful Project information can be seen at this
web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
J

julnar

Thanks for this first insight
I saw the FAQ 37 about task fields to Assignement view
Unfortunatly I d'nt know anything about macro or VBA.
Regards
 
M

Mike Glen

Hi julnar,

I know very little about such code, but as I understand it, you have to copy
the code in the FAQ into the vba editor. Open it via Tools/Macros.../Visual
Basic Editor. In the little toolbar on the left, click the first tool to
View Code. Click in the box that opens and paste in the code from the FAQ.
Then, from the main menu, Run/RunSub/UserForm. Then, in the project , try
Tools/Macro/Macros... where you should see the TransferTask... macro
listed. Now, when you want to activate it, click on the macro and click
Run. This should transfer information from one view to the other.

I didn't write the macro, so I can't answer any questions on this. I leave
it to my fellow MVPs or other knowledgeable experts to step in if I've got
it wrong!

Mike Glen
Project MVP
 