D
DA
I baselined Friday. Resources sent me updates over the
weekend, which I accessed remotely Sunday night and now
this morning, back in the office, all the reources are
gone and the tasks are "Unassigned." The updated Actuals,
Remaining, etc is still with the associated tasks. Any
ideas? Ever seen this before?
weekend, which I accessed remotely Sunday night and now
this morning, back in the office, all the reources are
gone and the tasks are "Unassigned." The updated Actuals,
Remaining, etc is still with the associated tasks. Any