Imagine the situation:
1.I have succesfully established link between Project Server and AD on
resource level by setting AD group to be imported as resources
2. I synchronized them manually, everything as OK
3. I unlinked the AD group from Project mapping
4. I forced synchronization
5. I manually disabled all users on Project security level
6. I purged them from Project Server
7. I Linked the same AD group back as Project resource set
8. I forced synchronization.....
and now two questions:
- Project did not import the resources again. I can imagine why, but if
someone knows please let me also know ? Of course newly created users on AD
level ARE imported
- How to "completely erase the memory" of Project Server about resources
imported from AD in the past and import them again?
Thank you for help
best
Imagine the situation:
1.I have succesfully established link between Project Server and AD on
resource level by setting AD group to be imported as resources
2. I synchronized them manually, everything as OK
3. I unlinked the AD group from Project mapping
4. I forced synchronization
5. I manually disabled all users on Project security level
6. I purged them from Project Server
7. I Linked the same AD group back as Project resource set
8. I forced synchronization.....
and now two questions:
- Project did not import the resources again. I can imagine why, but if
someone knows please let me also know ? Of course newly created users on AD
level ARE imported
- How to "completely erase the memory" of Project Server about resources
imported from AD in the past and import them again?
Thank you for help
best