S
sperlunk
Here is what happens - my resource enters hours for the Monday, and I approve
them on Tuesday. When they enter Tuesdays hours and I approve them, I see
Monday's hours in black and Tuesday's hours in red. However, after approval
and I go back and look at the View history of past task changes under updates
it looks like Monday was recorded twice. We have not yet build an OLAP cube.
Why is this happening?
them on Tuesday. When they enter Tuesdays hours and I approve them, I see
Monday's hours in black and Tuesday's hours in red. However, after approval
and I go back and look at the View history of past task changes under updates
it looks like Monday was recorded twice. We have not yet build an OLAP cube.
Why is this happening?