J
jinesh
Here is what happens - As per our company policy, resources fill up
their timesheet everyday evening and I do approve them next day
morning.
Means my resource enters hours for the Monday, and I approve them on
Tuesday. When they enter Tuesdays hours and I approve them, I see
Monday's hours in black and Tuesday's hours in red.
However, after approval and I go back and look at the View history of
past task changes under updates it looks like Monday was recorded
twice. Not only this, but the total no. of hours for perticular
date/day also get multiplied. We have not yet build an OLAP cube.
Why is this happening? What are the options to avoide this? As i've
mentioned, we have to approve the task everyday. Also let me know if
we can control / clear this additional entries from backend.
Thanks and regards
Jinesh Dalal
their timesheet everyday evening and I do approve them next day
morning.
Means my resource enters hours for the Monday, and I approve them on
Tuesday. When they enter Tuesdays hours and I approve them, I see
Monday's hours in black and Tuesday's hours in red.
However, after approval and I go back and look at the View history of
past task changes under updates it looks like Monday was recorded
twice. Not only this, but the total no. of hours for perticular
date/day also get multiplied. We have not yet build an OLAP cube.
Why is this happening? What are the options to avoide this? As i've
mentioned, we have to approve the task everyday. Also let me know if
we can control / clear this additional entries from backend.
Thanks and regards
Jinesh Dalal