M
Maglez
Hello,
When I assign 2 engineers to a task of 4 days, that task gets reduced to 2
days, this assumes that 2 people are able to do a job twice as fast, but I
know that those 2 engineers working together produce as 1.7 men instead of 2.
How do you guys take this into account? Is Project able to recalibrate those
resources in the way I want?
Let me explain the way I do it and you guys can correct me...
I have my resources added through the Resource Sheet, in there, a resource
has a Max Units of 100%. However, on the Task Information, under the
Resources tab, I add the 2 resources I want to work on that task and I change
their Units to 85%, this will do that task at 1.7 rate, so the 4 days task
will be done on 2.35 days instead of 2 days.
Is this the correct way of accounting for this? Should I have something else
into account?
Thank in advance for any response, comment or link.
Regards,
Miguel Gonzalez.
When I assign 2 engineers to a task of 4 days, that task gets reduced to 2
days, this assumes that 2 people are able to do a job twice as fast, but I
know that those 2 engineers working together produce as 1.7 men instead of 2.
How do you guys take this into account? Is Project able to recalibrate those
resources in the way I want?
Let me explain the way I do it and you guys can correct me...
I have my resources added through the Resource Sheet, in there, a resource
has a Max Units of 100%. However, on the Task Information, under the
Resources tab, I add the 2 resources I want to work on that task and I change
their Units to 85%, this will do that task at 1.7 rate, so the 4 days task
will be done on 2.35 days instead of 2 days.
Is this the correct way of accounting for this? Should I have something else
into account?
Thank in advance for any response, comment or link.
Regards,
Miguel Gonzalez.