Resources -Is this possible?

C

cbjames

(1) The company produces concrete panels
(2) They can produce 20,000 s.f. each day (mon-fri)
(3) They have continous orders for X number of s.f. due
on specific dates.
I wanted to set up a resource of 20,000 s.f. a day;
attach to a calendar; schedule the orders and let Project
produce a schedule based on the 20,000 s.f. a day
capicity and the due dates of the orders. I have read
everything and this may NOT be possible.
I am open to ANY suggestions. Help I am in a bid.

Thanks!
 
J

Jan De Messemaeker

Hi again,

I replied this to your direct mail
In summary: no problem, Resoruc Leveling does that, but you have to convert
orders into time needed on 'the capacity'.
 