Resources less than calendar hours but still overallocated.

C

Chris H

Similar question already been posted but solution didn't work for me. I have
a resource (person) working to an 8 hour day calendar. I have one task set
over 2 weeks which they spend 30 minutes on each day. I have another task for
the same resource which is using an hour per day over 3 days in parallel with
the previous task. However, it's flagged up as overallocated at 1.5 hours. If
I drop the 2nd task to 30 mins then total is 1 hour and marked as
unallocated. Looking at the resource usage the person doesn't seem able to
work more than 1 hour per day even though they are set to an 8 hour calendar.
 
S

Steve House [MVP]

Display the times of the tasks. If the times the tasks are running each day
overlap the resource is overalloczted even if the total time is well under
his max.
 
G

Gérard Ducouret

Hello Chris,
I tried again and everything works well for me.
Could you send me an excerpt of your project with the 2 tasks ?

Gérard Ducouret [Project MVP]

Chris H said:
Similar question already been posted but solution didn't work for me. I have
a resource (person) working to an 8 hour day calendar. I have one task set
over 2 weeks which they spend 30 minutes on each day. I have another task for
the same resource which is using an hour per day over 3 days in parallel with
the previous task. However, it's flagged up as overallocated at 1.5 hours. If
I drop the 2nd task to 30 mins then total is 1 hour and marked as
unallocated. Looking at the resource usage the person doesn't seem able to
work more than 1 hour per day even though they are set to an 8 hour
calendar.
 