Resources Names column (work instead of percentage)

J

jackie

Hello

I would like to be able to show in the Gnatt View in the column for
Resources Names, the name of the Resources and the work in hours as opposed
to a %

Many thanks
J
 
D

Dale Howard [MVP]

Jackie --

This is not possible. By default, the Resource Names column shows the names
of each resource assigned to the task, plus their assignment Units value if
less than 100%. If you need to see the Work hours for each resource, you
can temporarily insert the Work column to the right or left of the Resource
Names column. Hope this helps.
 
J

jackie

Thanks for your reply
Just to ensure I understand if I insert the work column I get the total work
for all resources, is there a way to show the work for each resource in this
column?

Many thanks again
J
 
D

Dale Howard [MVP]

Jackie --

Apply the Task Usage view and then click View - Table - Work. That will
show you the work for the resources assigned to each task. You can also
apply the Resource Usage view and click View - Table - Work. This will show
you the total Work for each resource, broken down by task. Hope this helps.
 