C
css34
I have several resources assigned to tasks in my project plan that is
published on the project server. the resources are set up with the same
permissions, however, some of the resources are not able to update the tasks
because the actual hours and remaining hours are read only on their tasks
sheet. I have confirmed that the tasks are not complete and have remaining
hours left on them... I'm stuck, please help.
published on the project server. the resources are set up with the same
permissions, however, some of the resources are not able to update the tasks
because the actual hours and remaining hours are read only on their tasks
sheet. I have confirmed that the tasks are not complete and have remaining
hours left on them... I'm stuck, please help.