B
Brian McCune
I posted a similar question earlier today, but feel that I have to clarify.
Why are my resources showing as overallocated when they are only set to work for 7.2 hours/day. Their typical work day is 8 hours (as is set in the calendar). Sometimes they show as overallocated when they only have 1 hour of work per day!
Sometimes when I remove some hours, and then re-assign them it fixes things, and the overallocation is gone, but I shouldn't have to do this!
This is sure to be a management question when I present the plan to the "higher-ups"!
-Brian
Why are my resources showing as overallocated when they are only set to work for 7.2 hours/day. Their typical work day is 8 hours (as is set in the calendar). Sometimes they show as overallocated when they only have 1 hour of work per day!
Sometimes when I remove some hours, and then re-assign them it fixes things, and the overallocation is gone, but I shouldn't have to do this!
This is sure to be a management question when I present the plan to the "higher-ups"!
-Brian