My project is effort driven and correctly allocated to all resources. Recently, I updated the Actual Work and set the project to automatically reschedule as of this Monday. Today, I reduced the work from 200 hours to 20 on a particular task and all of a sudden 8 resources in other tasks show as they are overallocated. Assuming that this is correct, what is the quickest way to resolve this problem.. Resource leveling does not seem to be working either.
My project is effort driven and correctly allocated to all resources. Recently, I updated the Actual Work and set the project to automatically reschedule as of this Monday. Today, I reduced the work from 200 hours to 20 on a particular task and all of a sudden 8 resources in other tasks show as they are overallocated. Assuming that this is correct, what is the quickest way to resolve this problem.. Resource leveling does not seem to be working either.