Hi Nilu,
when i add new resource in my project same resource is also added in
the resource pool?
If you're using a resource pool, no resources are added to projects, but only to
the pool.
Your different projects are using the resources out of the pool then.
To do this, create an empty project, add your resources there - this is your
resource pool. No project data are contained in this file.
To use the resources of the pool in a project:
Open the project itself.
Open the resource pool.
<Extras><Common use of resources...><Common resource usage...>
"Use resources from" [Your resource pool file]
After this you can choose in project in the column "resources" the resources
defined in the resource pool.
Maybe some menu topics called not exactly the way I wrote.
Sorry, my MSP is a german version...
Hope, this helps
Olaf