I often have multiple projects going on at once. Say 5-10 at happening at any
one time.
Each of these projects has an individual project plan that all share the
exact same Resource Sheet.
When I try and add all of these multiple project plans to one rolled up
version the resources from each plan copy themselves to the Resource Sheet of
the rollup.
Since each individual project plan uses the exact same resources, ordered in
exactly the same way, can't the Resource sheet just stay the same?
Is there anyway to make this happen without having MS Project Server?
one time.
Each of these projects has an individual project plan that all share the
exact same Resource Sheet.
When I try and add all of these multiple project plans to one rolled up
version the resources from each plan copy themselves to the Resource Sheet of
the rollup.
Since each individual project plan uses the exact same resources, ordered in
exactly the same way, can't the Resource sheet just stay the same?
Is there anyway to make this happen without having MS Project Server?