B
Brian McCune
We have a project that has a start date of June 1st, 2004.
There was a great deal of work that was completed from May 25th - June 6th. When I view my resources in the GANTT chart, they all show as overallocated for these weeks. All of these tasks (from May 25th - June 6th) are 100% complete.
Is there a way to depict historical data without piling up all of the work on the front end of the project?
-Brian
There was a great deal of work that was completed from May 25th - June 6th. When I view my resources in the GANTT chart, they all show as overallocated for these weeks. All of these tasks (from May 25th - June 6th) are 100% complete.
Is there a way to depict historical data without piling up all of the work on the front end of the project?
-Brian