P
Patrick
What can I do to be able to use the full day when assigning resources to a
task?
For example, a resource is available 100% and is assigned to a task for 6
weeks (or 30 days) but when you look at the total work effort days, it shows
29 days. When I manually adjust to fully utilize the whole day (from the 1st
and last week) to display 30 days, it comes up red. Why is it showing
overallocation?
I changed the leveling to 'minute by minute' but that makes no difference.
It appears that you need to allow 'free' time before and after a task.
task?
For example, a resource is available 100% and is assigned to a task for 6
weeks (or 30 days) but when you look at the total work effort days, it shows
29 days. When I manually adjust to fully utilize the whole day (from the 1st
and last week) to display 30 days, it comes up red. Why is it showing
overallocation?
I changed the leveling to 'minute by minute' but that makes no difference.
It appears that you need to allow 'free' time before and after a task.