K
Kevin Slane
When I pull up the Resources Summary view in Project Center for one of my
projects, I can see that I have two resrouces that show a peak of about 170%.
I know they're overallocated, but I can't figure out a way (or a view) to
get Project Server to show me where the overallocation is occurring.
I've gone to the Resource Center and pulled up one of my resources and
clicked the View Availability, but he doesn't have anything that exceeds 8
hours. Am I doing this incorrectly?
projects, I can see that I have two resrouces that show a peak of about 170%.
I know they're overallocated, but I can't figure out a way (or a view) to
get Project Server to show me where the overallocation is occurring.
I've gone to the Resource Center and pulled up one of my resources and
clicked the View Availability, but he doesn't have anything that exceeds 8
hours. Am I doing this incorrectly?