I have resources that are not setup as MS Project user accounts since
they are not our company employess, just a subcontractros we are
using. So they are listed as resources but they have no login
accounts.
Is there a way to filter task for each individual resource, and if yes
what kind of options I have to view those filtered tasks? Is there a
posibility to see the tasks in a calendar view?
Thank you,