J
jackie
Hello
I wonder if you can help
I am in the Resource Usage Table and a specific Resource is flagged
over-allocated for today even if hours of work allocated for today are
5.6hrs
Task A - 8 hrs in total, spread over for 5 days (units 20%) from today for
next few days - 1.6hrs allocated to today
Task B - 2 hrs, duration 1 day, date today, (units 25%)
Task C - 2 hrs, duration 0.25 day, date today (units 100%)
The total of work is 5.6hrs, which means the resource has got scope for more
work. However, it shows overallocated. I would be interested in
understanding more about the logic of flagging the resource overallocated. I
changed the duration of task C to 1 day duration and the resource was no
longer overallocated. Is it to do with the relationship with the units of
allocation in thevday? Please can you explain further? Many thanks. J
I wonder if you can help
I am in the Resource Usage Table and a specific Resource is flagged
over-allocated for today even if hours of work allocated for today are
5.6hrs
Task A - 8 hrs in total, spread over for 5 days (units 20%) from today for
next few days - 1.6hrs allocated to today
Task B - 2 hrs, duration 1 day, date today, (units 25%)
Task C - 2 hrs, duration 0.25 day, date today (units 100%)
The total of work is 5.6hrs, which means the resource has got scope for more
work. However, it shows overallocated. I would be interested in
understanding more about the logic of flagging the resource overallocated. I
changed the duration of task C to 1 day duration and the resource was no
longer overallocated. Is it to do with the relationship with the units of
allocation in thevday? Please can you explain further? Many thanks. J