resources viewing reassigned tasks in PWA

A

Andy

I have some tasks in a few projects in which the resources assigned have
changed. When the resource who was removed from the task views their task
assignments in PWA the tasks still appear but have an x in the first field
which signifies that they are no longer assigned to that task. How do I
remove those tasks from their personal task list? I would only like the
tasks to appear on the resource who is responsible for doing the work's task
list.

Any suggestions would be greatly appreciated.

Thanks,
Andy
 
D

Dale Howard [MVP]

Andy --

Ask the former resource to select the task on his/her timesheet in PWA and
to click the Hide button. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top