G'Day Larry,
Purely for convenience, I'm going to refer to the 5x8 people as full-time
and the 4x10 people as part-time.
I am also going to be very brief.
1. Set up Project to accomodate your full-timers:
Tools>Options
Calendar (Tab)
Hours per day=8
Hours per week=40
Be aware that whenever you assign a "duration" or "work" of
x days/weeks to a task, project uses these settings to calculate
what that means in terms of hours of work to be done
(Company Standard Day/Week - my terms).
While on this "Calendar" tab, adjust the default start/end times
carefully.
Make sure that the Business is "open" for (at least) 10 hours/day.
Work
will be scheduled ONLY during these hours and if they are not set
correctly
your part-timers may find themselves standing OUTSIDE THE DOOR for
part of their 10-hour day - and your schedule will go to hell....
2. Set up your Project Calendar for the full-timers - ie normal 5 x 8 hour
days,
Monday to Friday. (THIS MUST MATCH EXACTLY the hours/day and
hours/week in 1 above, or you will get anomolies in the Gantt
Chart.)
3. Set up a Special Calendar for the part timers - Say Mon-Thu @ 10
hours/day
Friday non-working.
4. For simplicity, estimate durations/work etc in hours - if this is not
convenient,
then remember (Standard) days (of work) are 8 hours (NEVER 10) ,
(Standard) weeks are 40 hours (Company Standard Day/Week).
5. Because your workers ALL work 40 hours per week, there will be few (if
any) anomolies on the Gantt Chart.
However for future reference:
If your part-timers worked only 8 hours per day (instead of
10), and
you assigned them to a 1 (Company) week task, then the duration
would be 5 (Company) days, but the Gantt Bar would be 6 days
long [6 (Company) working days INCLUDING the friday they
don't work].
I hope this helps.
--
Regards,
Pat Garard
Australia
_______________________
Larry said:
I am currently trying to schedule a project where some of the people work
4
10 hour days and some of the people work 5 8 hours days. I can not get
MS
Project 2003 to support both 8 hour and 10 hour days. Can this be done?