C
charles14
We are scheduling tasks for about 200 engineers each one being a resource
because of there skill sets. Every three or four weeks they will have a duty
week where they are available for emergent work for 7 days. During this time
there is certain work that cannot be assigned to them so the managers want
to see who has the duty on resource usage. I have loaded them tasks of 7 days
with resouces assigned at zero work.
On resource usage view this shows up as "0h" on the first day of duty and
then nothing shows for the remaining six days. If I assign any work at all,
even 1 hour spread over the seven days, the resource starts showing up as
overscheduled when they actually are scheduled to their 8 hours per day
available.
Is there any method to get duty to show on resource usage for the full seven
day period and not just the first day?
Charles14
because of there skill sets. Every three or four weeks they will have a duty
week where they are available for emergent work for 7 days. During this time
there is certain work that cannot be assigned to them so the managers want
to see who has the duty on resource usage. I have loaded them tasks of 7 days
with resouces assigned at zero work.
On resource usage view this shows up as "0h" on the first day of duty and
then nothing shows for the remaining six days. If I assign any work at all,
even 1 hour spread over the seven days, the resource starts showing up as
overscheduled when they actually are scheduled to their 8 hours per day
available.
Is there any method to get duty to show on resource usage for the full seven
day period and not just the first day?
Charles14