W
Weerayuth S.
Dear Sirs
I need help.
We are using MS Project 2003 EPM with PWA.
I created one project and enter resource assignment info and then published
the project. I can see resources' workload in Resource usage view.
But I don't know why the resources workload data of this project did not
show in Resource Portfolio Analyzer view. (The work load from other projects
is showed.)
(In the past I found this same problem; and I only have to wait 1 day due to
the OLAP cube update at 0:00 every night.)
But this time I have no idea what I did wrong.
If any one can help or pleasse suggest what I did wrong, please help.
Thank you very much in advanced.
I need help.
We are using MS Project 2003 EPM with PWA.
I created one project and enter resource assignment info and then published
the project. I can see resources' workload in Resource usage view.
But I don't know why the resources workload data of this project did not
show in Resource Portfolio Analyzer view. (The work load from other projects
is showed.)
(In the past I found this same problem; and I only have to wait 1 day due to
the OLAP cube update at 0:00 every night.)
But this time I have no idea what I did wrong.
If any one can help or pleasse suggest what I did wrong, please help.
Thank you very much in advanced.