stone

I has installed ProjectServer2007 and SQL2000(SP4), I published a project and
assigned some tasks to my team members ,but when the team members entered to
PWA, they could not update tasks, I didn't close the tasks, and I don't know
why, I need help.
 
P

Paul Conroy

Can you expand a little ?

What part of updating their tasks was not working?

Could they see them but not update them?
Could they not see them?
Did they get an error?
Are you updating through timesheets or task updates?
 
S

stone

They could see tasks that assigned to them but they coun't enter progress
for the tasks, and there was no error
 
S

stone

Thank you .
The team member can see tasks that assign to them, they can't erter progress
in "my task" page, and there was no error. When they open a task with task
assign detail, the task name is gray, the calculation again and save button
are gray too, and there was no error.
 