D
Dappa
MS Project 2007. Hi, I would like project to send out automatically,
scheduling updates to the contractors I use in my construction business. Is
there anyway of doing this?
Also is there a way of forcing a task to automatically finish on a
particluar day?
Example if we were pouring concrete, I would want that task to finsh on the
day it was started.
Or can I force a task to be automatically started the following work day
after the completion of all predessor tasks the that effect that task.
Example: All the tasks required to pour the concrete are completed, then the
concrete task is automatically scheduled for the next work day.
Work hard ... Play hard
scheduling updates to the contractors I use in my construction business. Is
there anyway of doing this?
Also is there a way of forcing a task to automatically finish on a
particluar day?
Example if we were pouring concrete, I would want that task to finsh on the
day it was started.
Or can I force a task to be automatically started the following work day
after the completion of all predessor tasks the that effect that task.
Example: All the tasks required to pour the concrete are completed, then the
concrete task is automatically scheduled for the next work day.
Work hard ... Play hard