Would like any suggestion on to handle a scenario described below using
MS-Project. We have work-around but wondered if there is more graceful
way to resolve.
Resource-1 is assigned to work on Task-1 and Task-2 and each task takes
two weeks time. Task-2 is scheduled to start with a week lag from the
start of Task-1. Resource-1 should be assigned to these two tasks 100%
except during the overlap period (2nd week) when he is expected to work
on both tasks simultaneously (50% on each task).
thanks,
Naomi
MS-Project. We have work-around but wondered if there is more graceful
way to resolve.
Resource-1 is assigned to work on Task-1 and Task-2 and each task takes
two weeks time. Task-2 is scheduled to start with a week lag from the
start of Task-1. Resource-1 should be assigned to these two tasks 100%
except during the overlap period (2nd week) when he is expected to work
on both tasks simultaneously (50% on each task).
thanks,
Naomi