As I work with a resource pool for my projects, when I look at the resource
usage to relocate the overloaded resource I never can tell which project the
assignments belong to! Any ideas?

TXS

Silene
 
K

Kirsten

This was pretty much my same question. How do you get the next level down
from the Project Name?
 
K

Kim Zimmerman

Hi, switch your view to resource allocation and you will get a split screen, then at the bottom screen click on Task Name, View, more views, select Resource Form, apply, then when you select a resource you will see the all the projects associated with that resoruce and tasks.



Silene wrote:

resourse usage
18-Mar-10

As I work with a resource pool for my projects, when I look at the resourc
usage to relocate the overloaded resource I never can tell which project th
assignments belong to! Any ideas

TX

Silene

Previous Posts In This Thread:


Submitted via EggHeadCafe - Software Developer Portal of Choice
DataContractSerializer Basics
http://www.eggheadcafe.com/tutorial...c-94d2f3b1b265/datacontractserializer-ba.aspx
 
S

Silene

Thank you Jan, I didn't think doing that, it is simple.
Also I did what Kim suggest and I will try.
The WBS code seems more complicated, I didn't try yet.

Thanks,

Silene
 