Hello everyone,
i am working with project 2016.
I am blocking on a basics error (i think) and i don't know why.
when i am scheduling a task and add one or several ressource i can chose directly allocation of this ressource. Let admit that we chose 50% for a task of 1 day ==> ms project calculate the work which sill be 4hours (my day is 8)
However, i finally discover that my work will be 6hours instead of 4.
Allocation of the ressource (in the table ressource allocation) is updated and the value in the table is 75%. Nevertheless, in the filed allocation rate and in the gantt view my ressource keep the originial 50% that i gave it to him...
Why ms project doesn't update this field ? did you alreday face this problem ??
Thanks by advance !!
Have a nice day !
Florian
i am working with project 2016.
I am blocking on a basics error (i think) and i don't know why.
when i am scheduling a task and add one or several ressource i can chose directly allocation of this ressource. Let admit that we chose 50% for a task of 1 day ==> ms project calculate the work which sill be 4hours (my day is 8)
However, i finally discover that my work will be 6hours instead of 4.
Allocation of the ressource (in the table ressource allocation) is updated and the value in the table is 75%. Nevertheless, in the filed allocation rate and in the gantt view my ressource keep the originial 50% that i gave it to him...
Why ms project doesn't update this field ? did you alreday face this problem ??
Thanks by advance !!
Have a nice day !
Florian