Q

question

Hi,

I have created a resource assignment view, in which I want display a task
level graphical indicator. It has a formula ssociated with it also. Bu t this
indicator is not getting displayed in the report, it is just showing the
formula result in numbers and no lights. Initially it was not showing any
value, so I updated the db value for assigment rolldown to true.

Can anybody help me with this. Any pointers will be helful.

Thanks.
 
J

Jan De Messemaeker

Hi,

What exactly is "a resoruce assignment view"?
If it is a view copied from the Resource Usage view, that one doesn't show
tasks, only assignments.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
Q

question

yes. It is a resource usage view.
how can I make a enterprise field ass a assignemnt column?
 
J

Jan De Messemaeker

Hi,

One cannot customize an assignment field.
In Project 2007 you can have the value of a customized task field or from a
customized resource field roll down into the assignment field - in 2007 each
assignment has two values for each customized field, incredible but true-
but you cannot have graphical indicators in an assignment field.

For a better understanding you can also read faqs 37 and 51 at
http://project.mvps.org/faqs.htm

Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top