Hi,
Does anybody know how to level resource in folowing configuration:
Task 1, work = 12d resource 1 at 60%
Task 2, work = 12d resource 1 at 60%
(Resource 1 unit = 100%, 5 days per week)
MSP Levels Task 2 starting at the enf of Task1 - it is wrong-
Ressource 1 as availibilty ( 2d per week) for task 2 - Task 2 should start
in // of task 1
Right leveling should be 3days for task1 and 2 days for task2 in 4 weeks and
for days in last week for task2.
It seems to be a weakness of MSP is it true ?
Thanks
Does anybody know how to level resource in folowing configuration:
Task 1, work = 12d resource 1 at 60%
Task 2, work = 12d resource 1 at 60%
(Resource 1 unit = 100%, 5 days per week)
MSP Levels Task 2 starting at the enf of Task1 - it is wrong-
Ressource 1 as availibilty ( 2d per week) for task 2 - Task 2 should start
in // of task 1
Right leveling should be 3days for task1 and 2 days for task2 in 4 weeks and
for days in last week for task2.
It seems to be a weakness of MSP is it true ?
Thanks