Kristine
I'm trying to change the ressource usage view for a file with multiple
projects so that I have a roll up for each project. The list is as follows:
Project 1
-Task1
--Ressource 1
--Ressource 2
-Task 2
--Ressource 1
--Ressource 3
-Task 3
--Ressource 3
Project 2
-Task1
--Ressource 2
--Ressource 5
-Task 2
--Ressource 3
--Ressource 4
-Task 3
--Ressource 1
etc
If I use the sort function I can sort my data in this order but the roll up
lines per ressource end in the end of the list. I would like to have roll ups
for each project instead. The structure of the ressource usage view is great
(and needed)- with the timeline and the time indications per day/week/month.
Does anyone know how to do this?
Looking forward to your answers.
Thank you
projects so that I have a roll up for each project. The list is as follows:
Project 1
-Task1
--Ressource 1
--Ressource 2
-Task 2
--Ressource 1
--Ressource 3
-Task 3
--Ressource 3
Project 2
-Task1
--Ressource 2
--Ressource 5
-Task 2
--Ressource 3
--Ressource 4
-Task 3
--Ressource 1
etc
If I use the sort function I can sort my data in this order but the roll up
lines per ressource end in the end of the list. I would like to have roll ups
for each project instead. The structure of the ressource usage view is great
(and needed)- with the timeline and the time indications per day/week/month.
Does anyone know how to do this?
Looking forward to your answers.