I have a resource scheduled at 20% on a task, so 1 day per week, for a 5 days
job.
I am lucky, this resource was free and completed the task in the same week,
so he was working 100% on the task
Why is the end milestone is not updated to show that the project will finish
sooner? If the guy worked at 100% but he were sheduled at 20%, I think the
project will finish 4 days in advance?
Thanks