I've already created my ressource pool with different rates tables for each ressource when applicable. For example Table A = 500$ a day, table B = 400 $ a day and so on. I work in Project 2003
When I create my project team, I selected the appropriate ressources in the ressource pool and I assign these ressources to the tasks of my project
My problem is when I want to use a rate table different than Table A, all the other tables show 0,00 $ as rate
What can I do to solve this