Ressources rate table in ressource pool

Y

Yves

I've already created my ressource pool with different rates tables for each ressource when applicable. For example Table A = 500$ a day, table B = 400 $ a day and so on. I work in Project 2003

When I create my project team, I selected the appropriate ressources in the ressource pool and I assign these ressources to the tasks of my project

My problem is when I want to use a rate table different than Table A, all the other tables show 0,00 $ as rate

What can I do to solve this

Yves
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top