Hi,
I am facing a problem. While uploading projects on project server, we forgot
to create baseline, now most of the projects are on mid way, but in the
absence of baseline, we are unable to get reliable reports from project
server. If we define baseline now, it will take the figures which is shown in
"Work" field as on today. MS Project uses to update the "Work" field after
getting Actual work information. But we need to get original baseline work
and other cost related information.
As per current version, we cant replace project on project server as it
contains actual efforts from timesheets.
Can anyone please tell how can we get original baseline figures on ongoing
projects ?
Thanks & Regards,
chinnu
I am facing a problem. While uploading projects on project server, we forgot
to create baseline, now most of the projects are on mid way, but in the
absence of baseline, we are unable to get reliable reports from project
server. If we define baseline now, it will take the figures which is shown in
"Work" field as on today. MS Project uses to update the "Work" field after
getting Actual work information. But we need to get original baseline work
and other cost related information.
As per current version, we cant replace project on project server as it
contains actual efforts from timesheets.
Can anyone please tell how can we get original baseline figures on ongoing
projects ?
Thanks & Regards,
chinnu