B
Bawbee
I have a project where the work started on 23-Jul-08 and proceeded for 3 days
on preparatory tasks. There follows a 'split' where no further work takes
place until 12-Jan-09. I have an unlinked split task that shows the initial
work (23-Jul-08 to 25-Jul-08) and the second portion shows the second portion
of teh project (12-Jan-09 to 13-Feb-09) - this shows a correct duration of 29
days. The problem I want to work-around is that the summary task shows a
duration of 149 days (23-Jul-08 to 13-Feb-09).
Is there anyway to show the split in the summary bar and for it to show only
the duration where tasks are being worked on?
on preparatory tasks. There follows a 'split' where no further work takes
place until 12-Jan-09. I have an unlinked split task that shows the initial
work (23-Jul-08 to 25-Jul-08) and the second portion shows the second portion
of teh project (12-Jan-09 to 13-Feb-09) - this shows a correct duration of 29
days. The problem I want to work-around is that the summary task shows a
duration of 149 days (23-Jul-08 to 13-Feb-09).
Is there anyway to show the split in the summary bar and for it to show only
the duration where tasks are being worked on?