S
Sandra
I have created a master schedule with several subordinate linked schedules.
I would like to share the same schedules with both the Finance Department and
Engineering, without revealing the cost tables to Engineering.
Is there any way to allow someone to modify a schedule, but not allow them
to see the cost tables?
I've tried copying the all the schedules to a different directory and
modifying the resource pool each time by setting the costs to 0. It works
for now, but it is time consuming and it would be easy to make a mistake. I
hope there is a better way.
BTW: I am using MSProject 2002 and I do not have Project Server.
Thanks,
Sandra
I would like to share the same schedules with both the Finance Department and
Engineering, without revealing the cost tables to Engineering.
Is there any way to allow someone to modify a schedule, but not allow them
to see the cost tables?
I've tried copying the all the schedules to a different directory and
modifying the resource pool each time by setting the costs to 0. It works
for now, but it is time consuming and it would be easy to make a mistake. I
hope there is a better way.
BTW: I am using MSProject 2002 and I do not have Project Server.
Thanks,
Sandra